Hyderabad: Musi riverfront development on hold
Officials claimed to have identified
1,200 encroachments, survey to be conducted before demolition.
Hyderabad: Work on the development of
the Musi riverfront has been put on hold for a year now. The last time there
was any activity was in June last year when, following a High Court direction,
the Musi Riverfront Development Corporation (MRDC), in a kneejerk reflex,
announced a design competition.
An MRDC official now says that they
have identified 1,200 encroachments and that a social impact survey will be
conducted prior to their demolition. Officials have claimed that the project
will not see the light of day for at least four
Electronic Component Insights search
your component, compare prices, order your part, save time and money.
The election code of conduct gives
officials additional cover.
In June last year, the government
invited agencies to participate in a design contest for urban landscaping and
riverfront development. Officials neither finalised the designs nor put them in
the public domain.
The MRDC has proposed to take up the
project in two phases. Under Phase-I, that was scheduled to be completed by the
end of March, up to 5 km between Puranapul and Chaderghat was to be beautified.
Phase-II comprises a Musi corridor
with east-west connectivity in the form of a skyway.
Additionally, river conservation and
beautification from the outfall of Himayatsagar and Osmansagar on the west to
the ORR at Gowrelli on the east, measuring 57.5 km, is part of the project.
This work is expected to take two-and-a-half years.
The Hyderabad Metropolitan Water
Supply and Sewerage Board has been commissioned to undertake the diversion of
42 channels through which sewage enters the river. It has also been entrusted
with the job of setting up a comprehensive sewage treatment plant.
The government has allocated Rs 377.35
crore for the MRDC, against the total cost of Rs 1,665 crore. Sources said the
funds had not been released.
The High Court on August 21 last year
had said the MRDC which was meant for the revival of the Musi river was not
acting in accordance with its principles. The court said, "In fact, with
the construction of pathways on its sides in the name of beautification, the
river is actually beginning to shrink. Stents do not work if the veins leading
to the heart are blocked by cholesterol and the heart needs bypass surgery."
The court asked the MRDC to confirm
the number of encroachments. Following this, the MRDC finally verified revenue
records and identified 56 encroachments in Medchal district, 275 in Ranga Reddy
district and 738 in Hyderabad district.
An MRDC official said that the
corporation would conduct a social impact assessment and submit it to the
government prior to taking up a drive to demolish the encroachments. When asked
about the status of the Musi beatification project, he said that the ball was
in the government's court and it had to take a decision now.